Further to the answer to question S3W-5790 by Shona Robison on 5 November 2007, why the project team will take until December 2008 to produ…
The question
To ask the Scottish Executive, further to the answer to question S3W-5790 by Shona Robison on 5 November 2007, why the project team will take until December 2008 to produce an action plan on NHS wheelchair and seating services.
The answer
NHS Wheelchair and Seating servicesprovide wheelchairs to those with impaired mobility arising from clinical conditions.However, wheelchair provision also includes input and interventions from a broadspectrum of agencies such as social care, housing and education services in additionto health. To successfully address the issues raised by the review, engagement withand agreement from all agencies in taking forward proposed actions is essential.
The patient focussed approachis central to the development of redesigned services to address the recommendationsfrom the review and continue the elimination of excess waits. Some of the improvementsalready underway are referred to in the answer to question S3W-7724 on 16 January 2008. Allanswers to written parliamentary questions are available on the Parliament’s website,the search facility for which can be found at http://www.scottish.parliament.uk/webapp/wa.search.
The project team will assessthe recommendations from the review as part of the development of an action planand ensure that changes proposed are evidence based and cost effective to NHS Scotlandand its partners.
Producing a fully costed, robustand realistic action plan that will underpin the provision of modern and sustainableNHS wheelchair and seating services in Scotland will require until December 2008. This time period includes12 weeks for public consultation on the draft action plan prior to finalisation.
The patient focussed approachis central to the development of redesigned services to address the recommendationsfrom the review and continue the elimination of excess waits. Some of the improvementsalready underway are referred to in the answer to question S3W-7724 on 16 January 2008. Allanswers to written parliamentary questions are available on the Parliament’s website,the search facility for which can be found at http://www.scottish.parliament.uk/webapp/wa.search.
The project team will assessthe recommendations from the review as part of the development of an action planand ensure that changes proposed are evidence based and cost effective to NHS Scotlandand its partners.
Producing a fully costed, robustand realistic action plan that will underpin the provision of modern and sustainableNHS wheelchair and seating services in Scotland will require until December 2008. This time period includes12 weeks for public consultation on the draft action plan prior to finalisation.