What level of financial support is committed by it and other government agencies to the redevelopment of the former Ravenscraig site.

Answered Asked by Jack McConnell Lab Lodged 5 Dec 2007

The question

To ask the Scottish Executive what level of financial support is committed by it and other government agencies to the redevelopment of the former Ravenscraig site.

The answer

Answered by Jim Mather on 19 Dec 2007 · 14 days after it was lodged, on time

The ScottishGovernment and its agencies have provided financial support for theredevelopment of the former Ravenscraig site as follows:
ScottishEnterprise has approved funding of up to £12.869 million to the Ravenscraigproject for infrastructure costs in phase one.
CommunitiesScotland has not entered into any legal commitment to provide financial supportto Ravenscraig, but has indicated its intention to provide Housing AssociationGrant to support the development of 350 affordable houses during the lifetimeof the project. Communities Scotland is in discussion with local housingassociations, North Lanarkshire Council and Ravenscraig partnership about thisfuture contribution.
The ScottishFunding Council has agreed to provide funding support of up to £42.44 milliontowards Motherwell College’s new campus project.