The question

To ask the Scottish Executive, further to the answer to question S3W-5931 by Stewart Stevenson on 12 November 2007, what the projected traffic growth is for the two stretches of road from 2004 to 2014.

The answer

Answered by Stewart Stevenson on 11 Dec 2007 · 13 days after it was lodged, on time

The traffic growthrate between Mollinsburn to Auchenkilns is expected to be approximately 2.9% perannum, and at a rate of 2.3% per annum between Auchenkilns to Haggs. These ratesof growth are based on projections to the year 2025 using local transport modelsthat utilise estimates based on a national strategic model.

In the Official Report

No contribution in the Official Report cites S3W-07129 by reference.