Written Question · S3W-05075 · Session 3
What the cost breakdown is of the £11.5 million increase in subsidy provided to Calmac Ferries Ltd to operate the new tender agreement.
The question
To ask the Scottish Executive what the cost breakdown is of the £11.5 million increase in subsidy provided to Calmac Ferries Ltd to operate the new tender agreement.
The answer
The increase in subsidyis approximately £11 million when the year beginning 1 October 2007 (the first year of the new contract) is compared withthe year ending 31 March 2007. A range of factors contributes to this increase.These include inflation (£3.2 million), increased employer pension contributions(£2.3 million), increased third party harbour charges (£2.2 million) and additionalleasing and running costs for new vessels (£1.9 million).
In the Official Report
No contribution in the Official Report cites S3W-05075 by reference.