Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S3W-03988 · Session 3

Whether it will guarantee that the establishment of a Scottish futures trust, as promised in the SNP manifesto, will not cause the schedule…

Answered Asked by Tom McCabe Lab Lodged 4 Sep 2007

The question

To ask the Scottish Executive whether it will guarantee that the establishment of a Scottish futures trust, as promised in the SNP manifesto, will not cause the scheduled refurbishment of St Mark’s Primary School in Hamilton to be postponed or cancelled.

The answer

Answered by John Swinney on 11 Sep 2007 · 7 days after it was lodged, on time

The refurbishmentof St Mark’s Primary School in Hamilton is a matter for South Lanarkshire Councilwhich has a statutory responsibility to provide and maintain school buildings.
There are severalprocurement options open to public sector procuring bodies and it is their responsibilityto assess which is most appropriate for any investment they are undertaking. Asregards the Scottish Futures Trust, work on the design aspects is underway, andwe believe it will be able to deliver better value arrangements for major publicinfrastructure projects. We will make an announcement when we are ready to explainit in more detail.

In the Official Report

No contribution in the Official Report cites S3W-03988 by reference.