Written Question · S3W-01420 · Session 3
Further to the answer to the first supplementary to question S3O-305 by Stewart Stevenson on 21 June 2007 (Official Report c. 997), whether…
The question
To ask the Scottish Executive, further to the answer to the first supplementary to question S3O-305 by Stewart Stevenson on 21 June 2007 (Official Report c. 997), whether it will ensure that the design and construction of the new crossing increases public transport capacity across the Forth.
The answer
Provision for enhanced publictransport will be incorporated into the replacement crossing in order to managepredicted increase in demand for cross-Forth travel.
In the Official Report
No contribution in the Official Report cites S3W-01420 by reference.