Further to the answer to question S3W-222 by Stewart Stevenson on 8 June 2007, what the current cost estimates are for the construction of …
The question
To ask the Scottish Executive, further to the answer to question S3W-222 by Stewart Stevenson on 8 June 2007, what the current cost estimates are for the construction of the Borders railway.
The answer
The current cost estimategiven by the Promoter in their Outline Business Case is £130.6 million at 2002 prices.This figure excludes Optimism Bias and includes the additional station at Stow. The promoter’s estimate is currently subject to reviewby Transport Scotland.