Written Question · S2W-32582 · Session 2
How the estimated final cost of the A68 Dalkeith Northern Bypass was calculated.
The question
To ask the Scottish Executive how the estimated final cost of the A68 Dalkeith Northern Bypass was calculated.
The answer
The estimated total cost of theA68 Dalkeith Northern Bypass comprises the following costs:
| Estimated Total Cost (Excluding VAT)
(£ Million)
Design costs
| 2.4
Land
| 2.4
Advance works
| 1.6
Estimated total cost of protester activity
| 1.6
Contract tender sum
| 29.9
Estimated cost of grouting works for ground consolidation
| 5.9
Moving public utilities 292,500 inc VAT)
| 1.1
Site supervision
| 0.7
Total estimated cost
| 45.6
| Estimated Total Cost (Excluding VAT)
(£ Million)
Design costs
| 2.4
Land
| 2.4
Advance works
| 1.6
Estimated total cost of protester activity
| 1.6
Contract tender sum
| 29.9
Estimated cost of grouting works for ground consolidation
| 5.9
Moving public utilities 292,500 inc VAT)
| 1.1
Site supervision
| 0.7
Total estimated cost
| 45.6
In the Official Report
No contribution in the Official Report cites S2W-32582 by reference.