Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S2W-32582 · Session 2

How the estimated final cost of the A68 Dalkeith Northern Bypass was calculated.

Answered Asked by Mark Ballard Green Lodged 19 Mar 2007

The question

To ask the Scottish Executive how the estimated final cost of the A68 Dalkeith Northern Bypass was calculated.

The answer

Answered by Tavish Scott on 29 Mar 2007 · 10 days after it was lodged, on time

The estimated total cost of theA68 Dalkeith Northern Bypass comprises the following costs:

| Estimated Total Cost (Excluding VAT)
(£ Million)

Design costs
| 2.4

Land
| 2.4

Advance works
| 1.6

Estimated total cost of protester activity
| 1.6

Contract tender sum
| 29.9

Estimated cost of grouting works for ground consolidation
| 5.9

Moving public utilities 292,500 inc VAT)
| 1.1

Site supervision
| 0.7

Total estimated cost
| 45.6

In the Official Report

No contribution in the Official Report cites S2W-32582 by reference.