Further to the answer to question S2W-28485 by Peter Peacock on 4 October 2006, whether any further awards have been made towards renewable…
The question
To ask the Scottish Executive, further to the answer to question S2W-28485 by Peter Peacock on 4 October 2006, whether any further awards have been made towards renewable energy installation projects for schools, showing also the amount awarded to each local authority.
The answer
This information requested isset out in the following table;
Local Authority
| Scottish Community and Householder Renewables Initiative (SCHRI)
Grant (subsequent to information provided in S2W-28485)
Aberdeen City
| £23,701
Fife
| £2,641.55
Highland
| £70,546
North Lanarkshire
| £109,576
Stirling
| £15,000
In addition, since the questionin October, we have offered grant funding of £400,000 to support the installationof biomass heating in the Perth and Kinross PPP Schools Project.
Local Authority
| Scottish Community and Householder Renewables Initiative (SCHRI)
Grant (subsequent to information provided in S2W-28485)
Aberdeen City
| £23,701
Fife
| £2,641.55
Highland
| £70,546
North Lanarkshire
| £109,576
Stirling
| £15,000
In addition, since the questionin October, we have offered grant funding of £400,000 to support the installationof biomass heating in the Perth and Kinross PPP Schools Project.
In the Official Report