What percentage of its budget will be taken up by PFI/PPP commitments in each of the next 10 years, broken down by department.
The question
To ask the Scottish Executive what percentage of its budget will be taken up by PFI/PPP commitments in each of the next 10 years, broken down by department.
The answer
The information requested isset out in the following table.
SE PPP Commitments as a Percentageof Departmental Budgets¹
Year
| Justice²
| Education
| Enterprise, Transport and Lifelong Learning
| Finance and Central Services
| Scottish Executive Total
2007-08
(estimate)
|
-
| 7.2
| 0.9
| 0.8
| 0.6
Notes:
1. The Departmental ExpenditureLimits (DEL) budget has been used which includes both operating and capital budgets.
2. A figure for 2007-08is not available.
The PPP commitments of the ScottishExecutive fall into two categories: the unitary charge for the Executive’s own PPPprojects and the support funding provided to local authority PPP projects. In thecase of the latter, the full unitary charge has not been shown as only the fundingprovided by the Executive is a commitment for the Executive.
The table only includes 2007-08as the Executive’s spending plans have only been formally approved at present upuntil that year.
SE PPP Commitments as a Percentageof Departmental Budgets¹
Year
| Justice²
| Education
| Enterprise, Transport and Lifelong Learning
| Finance and Central Services
| Scottish Executive Total
2007-08
(estimate)
|
-
| 7.2
| 0.9
| 0.8
| 0.6
Notes:
1. The Departmental ExpenditureLimits (DEL) budget has been used which includes both operating and capital budgets.
2. A figure for 2007-08is not available.
The PPP commitments of the ScottishExecutive fall into two categories: the unitary charge for the Executive’s own PPPprojects and the support funding provided to local authority PPP projects. In thecase of the latter, the full unitary charge has not been shown as only the fundingprovided by the Executive is a commitment for the Executive.
The table only includes 2007-08as the Executive’s spending plans have only been formally approved at present upuntil that year.