Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S2W-31923 · Session 2

Further to the answer to question S2W-31693 by Tavish Scott on 19 February 2007, how  the public and the Highland Regional Council were inf…

Answered Asked by Carolyn Leckie SSP Lodged 21 Feb 2007

The question

To ask the Scottish Executive, further to the answer to question S2W-31693 by Tavish Scott on 19 February 2007, how the public and the Highland Regional Council were informed of the length of toll period represented by the arrangement referred to in the answer.

The answer

Answered by Tavish Scott on 5 Mar 2007 · 12 days after it was lodged, on time

The anticipated length of thetoll period was set out in the Skye Bridge Assignation Statement,which was made available for public inspection in October and November 1991.

In the Official Report

No contribution in the Official Report cites S2W-31923 by reference.