Whether it still intends to reopen the Waverley railway line and, if so, when construction tendering will commence and what the maximum cos…

Answered Asked by David Davidson Con Lodged 20 Dec 2006

The question

To ask the Scottish Executive whether it still intends to reopen the Waverley railway line and, if so, when construction tendering will commence and what the maximum cost will be.

The answer

Answered by Tavish Scott on 19 Jan 2007 · 30 days after it was lodged, on time

The Scottish Executive is committedto the reopening of the Waverley railway line. Under the current programme,construction tendering will commence in summer 2008. The most recent estimateof the maximum cost provided by the Waverley Railway Partnership is £129.61million at 2002 prices.