Whether it will provide a breakdown of its budget for waste initiatives in 2007-08.

Answered Asked by Sandra White SNP Lodged 14 Nov 2006

The question

To ask the Scottish Executive whether it will provide a breakdown of its budget for waste initiatives in 2007-08.

The answer

Answered by Ross Finnie on 23 Nov 2006 · 9 days after it was lodged, on time

Our expected expenditure on thewaste initiatives line in 2007-08 is outlined as follows.
Body
| Amount (£)
| Main Purpose

Waste and Resources Action Programme (WRAP)
| 7,390,000
| To develop markets and infrastructure for recycled products and to carry out waste prevention work in relation to home composting and retailers.

INCREASE (grants for community recycling bodies)
| 2,500,000
| To provide grants to community recycling bodies to reduce, re-use and recycle waste, in line with the National Waste Plan.

Envirowise
| 2,300,000
| To provide advice to business on waste minimisation.

Scottish Waste Awareness Group (SWAG)
| 985,000
| To co-ordinate local information campaigns on using recycling facilities; to provide information to the public on reducing, re-using and recycling waste and to support work by WRAP.

Community Recycling Network for Scotland (CRNS)
| 500,000
| To develop the capacity of the community recycling sector.

REMADE Scotland
| 482,000
| To develop markets for recycled products.

Business Environment Partnership
| 430,000
| To provide advice to business on waste minimisation.

Eco-Schools
| 200,000
| To provide a framework for waste and environmental education in schools.

Administration of INCREASE
| 200,000
| To administer the INCREASE grants programme

Scottish Industrial Symbiosis Programme
| 50,000
| To facilitate arrangements between business to use by-products and minimise waste sent to landfill

Total
| 15,037,000
|


This table does not include expenditureon Keep Scotland Beautiful’s litter work and on a grant scheme for local authoritiesin relation to contaminated land. Similarly, it does not include £1.5 million transferredto the Enterprise, Transport and Lifelong Department from Landfill Taxconsequentials to support work on energy efficiency.