Written Question · S2W-28998 · Session 2

Further to the answer to question S2W-28407 by Tavish Scott on 6 October 2006, what the reasons are for the delay in the commencement date …

Answered Asked by Campbell Martin Ind Lodged 10 Oct 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-28407 by Tavish Scott on 6 October 2006, what the reasons are for the delay in the commencement date of the construction of an off-line improvement to the carriageway of the A737 at the Den, between Dalry and Beith; what the Executive’s source was for the earlier anticipated commencement date of June 2006, as referred to in the Minister for Transport’s letter to me dated 12 September 2005, and how many of the decisions referred to in the answer to question S2W-28407 had been reached prior to June 2006.

The answer

Answered by Tavish Scott on 9 Nov 2006 · 30 days after it was lodged, 2 days after it was due

The A737 Den Improvement Schemeis being promoted and funded by North Ayrshire Council.
The scheme programme, and measuringprogress against it, is the responsibility of North Ayrshire Council and requiresto fit in with other planned improvements on the route in order to manage the levelof disruption to the travelling public.
The scheme at the Den could bebrought forward if the scheme planned at Barrmill Road slips due to objections andno objections to the Den Orders are received. Progressing Transport Scotland’s elementsis dependent on the timely supply of all the necessary material from the councilincluding draft Orders, Environmental Report, draft Record of Determination, draftEnvironmental Statement (if required) Geotechnical Certification and design andconstruction details.
The Scottish Executive’s sourcefor the earlier anticipated start date of June 2006 advised to you in September2005 was North Ayrshire Council, and based on its anticipated programme at thattime.
Decisions relating to the principleof the council proceeding with the scheme on the Trunk Road were reached in May2003. Decisions taken relating to technical aspects, environmental and statutoryprocesses and programming have been on-going both prior to and since June 2006.This will continue as the council works through its programme until constructionof the scheme is complete.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for more informationif required.