What spare capacity is available on the national grid to transmit power from renewable sources.

Answered Asked by David Davidson Con Lodged 27 Sep 2006

The question

To ask the Scottish Executive what spare capacity is available on the national grid to transmit power from renewable sources.

The answer

Answered by Nicol Stephen on 27 Oct 2006 · 30 days after it was lodged, 2 days after it was due

The operational management ofgrid capacity is a matter for the regulator (Ofgem) and the owners and operatorsof the electricity grid. The grid networks in Scotland are currently owned andoperated by Scottish and Southern Energy and Scottish Power in their respectiveareas, whereas the transmission network operator is National Grid. The ScottishExecutive has discussions with these bodies on a regular basis.
The Forum for Renewable EnergyDevelopment is Scotland (FREDS) examined grid capacity, constraints and upgradesin its 2005 report, Scotland’s Renewable Energy: Realising The 2020 Target.The report found that the key upgrades for which Ofgem has approved funding couldallow the connection of 6.3 gigawatts (GW) of generation applications. The reportconcluded that these upgrades could accommodate 4.8GW of installed renewable capacity,over and above what is already installed and consented.

In the Official Report

No contribution in the Official Report cites S2W-28712 by reference.