Further to the answer to question S2W-28112 by Mr Tom McCabe on 13 September 2006, how the absence of centrally held procurement cost data …

Answered Asked by Stewart Stevenson SNP Lodged 14 Sep 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-28112 by Mr Tom McCabe on 13 September 2006, how the absence of centrally held procurement cost data impacts on the Executive’s ability to implement the McClelland Report on procurement.

The answer

Answered by Tom McCabe on 26 Sep 2006 · 12 days after it was lodged, on time

The report highlighted the lackof consistent data as a concern. In implementing the report’s recommendations the Executive intends to undertake additional work on identifying procurement expenditureacross the public sector. It should be noted, however, that this work will focusinitially on larger organisations with higher levels of procurement spending andthat comprehensive central data is not expected to be available for some time.

In the Official Report