Further to the answer to question S2W-26309 by Tavish Scott on 13 June 2006, whether it will carry out a new study into the feasibility and…

Answered Asked by Murdo Fraser Con Lodged 25 Jul 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-26309 by Tavish Scott on 13 June 2006, whether it will carry out a new study into the feasibility and cost of dualling the A9 in its entirety between Perth and Inverness.

The answer

Answered by Tavish Scott on 17 Aug 2006 · 23 days after it was lodged, on time

We are undertakinga Strategic Transport Projects Review (STPR) which will provide an opportunity toconsider future strategic investment priorities for all modes of transport acrossthe whole transport network in Scotland, includingtransport corridors, such as the A9 between Perth and Inverness. In addition to the Perth – Inverness corridor, being assessed through the (STPR).
I recently announcedthe outcome of the Route Action Strategy Study between Perth and Blair Atholl which identified £165million worth of potential long-term improvement work on the southern section of the A9 and recommended that more detailed analysis on this be carried out to confirmthe practicality. I have agreed to this further work being done to fully assessthe implications and practicalities of dualling between Perth and Pitlochry, provision of safe overtakingopportunities and reconstruction along this important, but environmentally sensitiveroute.

In the Official Report

No contribution in the Official Report cites S2W-27564 by reference.