The question

To ask the Scottish Executive what provision was made in any of the transactions in respect of the reconstruction of Hampden Park for the public purse to benefit from a share in any profit made in its running.

The answer

Answered by Patricia Ferguson on 17 Aug 2006 · 27 days after it was lodged, on time

No provisions were in place forthe public purse to benefit from the profits of running Hampden Park. However,provisions were put in place for a specificproportionate repayment of grant in the event of Queen’s Park Football Club Limitedselling, leasing (otherwise than for football matches) or disposing any interestin Hampden Park without the prior consent of the then Secretary of State for Scotlandor Scottish ministers. This provision for Phase I redevelopment lapsed in 2005 andfor Phase II is in place until 2010.