Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S2W-27184 · Session 2

What estimate it has made of the volume of minerals which will be required for the construction of the M74 Northern Extension; what its pol…

Answered Asked by Murray Tosh Con Lodged 29 Jun 2006

The question

To ask the Scottish Executive what estimate it has made of the volume of minerals which will be required for the construction of the M74 Northern Extension; what its policies are for sourcing the necessary minerals locally; what work it has carried out to satisfy itself that sufficient local mineral sources exist, to avoid large volumes of material being transported over long distances into Glasgow, and whether the statutory consents are in place to allow all minerals to be obtained, through extraction or recycling, from within acceptable transport distances.

The answer

Answered by Tavish Scott on 26 Jul 2006 · 27 days after it was lodged, on time

An analysis of the quantityof materials required and the proposed mitigation is described in some detailin the Environmental Statement prepared for the scheme a copy of which can be obtained from the Scottish Parliament’s Reference Centre (Bib. number 40051).
The sourcing of materials andany necessary statutory consents will be a commercial matter for the contractorfor the works. During the development of the scheme, preliminary investigationswere undertaken into potential sources of infill within Central Scotland. A number of these sources offer the potential for rail haulage to thesite.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for moreinformation if required.

In the Official Report

No contribution in the Official Report cites S2W-27184 by reference.