The question

To ask the Scottish Executive, further to the answer to question S2W-26487 by Allan Wilson on 8 June 2006, what the cost will be of the evaluation of the Skills for Business Network and how the evaluation will be funded.

The answer

Answered by Allan Wilson on 20 Jun 2006 · 12 days after it was lodged, on time

The total cost of the Skillsfor Business Network evaluation will be £86,638 excluding VAT. The evaluation isbeing funded by both the Scottish Executive and the Sector Skills Development Agency.

In the Official Report

No contribution in the Official Report cites S2W-26666 by reference.