Further to the answer to question S2W-15179 by Patricia Ferguson on 22 March 2005, how much funding each project has received and what the …
The question
To ask the Scottish Executive, further to the answer to question S2W-15179 by Patricia Ferguson on 22 March 2005, how much funding each project has received and what the timetable is for completion of each project.
The answer
The allocation to each projectwill be confirmed on approval of the related Stage Two application. Following continuedwork with lead councils and their partners to help finalise the development of theirrespective projects, the Executive and sportscotland will soon be approvingthe first of the Stage Two applications.
Thetimetable for completion of each project as it currently stands is as follows:
Lead Applicant
· Project
| Estimated Completion Date
Falkirk Council:
· Westfield Stadium
|
April 2008
Stirling Council:
· Forthbank
|
April 2008
City of Edinburgh Council:
· Sighthill Park
|
June 2011
· Hunters Hall
| March 2009
· Royal Commonwealth Pool
| January 2011
Aberdeen City Council:
· Linksfield
|
August 2008
Glasgow City Council:
· East End
|
August 2009
· Scotstoun
| May 2008
· Toryglen
| July 2008
North Lanarkshire Council:
· Ravenscraig
|
September 2008
Thetimetable for completion of each project as it currently stands is as follows:
Lead Applicant
· Project
| Estimated Completion Date
Falkirk Council:
· Westfield Stadium
|
April 2008
Stirling Council:
· Forthbank
|
April 2008
City of Edinburgh Council:
· Sighthill Park
|
June 2011
· Hunters Hall
| March 2009
· Royal Commonwealth Pool
| January 2011
Aberdeen City Council:
· Linksfield
|
August 2008
Glasgow City Council:
· East End
|
August 2009
· Scotstoun
| May 2008
· Toryglen
| July 2008
North Lanarkshire Council:
· Ravenscraig
|
September 2008