Further to the answer to question S2W-24710 by Rhona Brankin on 27 March 2006, whether competent authorities in Scotland proposing to agree…

Answered Asked by Mark Ruskell Green Lodged 30 May 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-24710 by Rhona Brankin on 27 March 2006, whether competent authorities in Scotland proposing to agree a plan or project of a type not specified by Regulations 54 to 85 of the Conservation (Natural Habitats, &c.) Regulations 1994 (as amended), notwithstanding a negative assessment of the implications for a European site, are required (a) to notify Scottish Ministers and (b) not to agree to the plan or project for a period of 21 days unless Scottish Ministers notify them that they may do so and, if not, what procedure such authorities are expected to follow.

The answer

Answered by Rhona Brankin on 14 Jun 2006 · 15 days after it was lodged, 1 day after it was due

Regulation 3(4) of the Conservation(Natural Habitats, &c.) Regulations 1994 requires every competent authority,in the exercise of its functions, to have regard to the requirements of the HabitatsDirective (92/42/EEC) so far as they may be affected by those functions. Competentauthorities are therefore obliged to comply with the procedures and requirementsspecified in Article 6 of the Directive, whether or not they are also bound by otherobligations.
As a matter of law, only plansor projects covered by Regulations 53A to 85 of the Conservation (Natural Habitats,&c.) Regulations 1994 are subject to the specific obligations, set out in Regulation49, to notify the Scottish ministers and to defer a decision for a period of 21days.
However, no competent authoritymay agree to a plan or project unless it has ascertained that (a) the plan or projectwill have no significant effect on a European site, or that (b) the integrity of the site will not be adversely affected, or that (c) site integrity will be adverselyaffected but that there is no alternative solution and the plan or project mustbe carried out for imperative reasons of overriding public interest. This legalobligation, and the associated procedural requirements, apply irrespective of whetherthe competent authority is operating under Regulation 3(4) or Regulations 53A to85.

In the Official Report