Written Question · S2W-25625 · Session 2
Further to the answer to question S2W-17526, whether the draft orders for the realignment of the A7 at Auchenrivock were lodged in late 200…
The question
To ask the Scottish Executive, further to the answer to question S2W-17526, whether the draft orders for the realignment of the A7 at Auchenrivock were lodged in late 2005 and when it now expects construction work to commence and to be completed.
The answer
Draft Orders for the A7Auchenrivock scheme were published on 12 May. Subject to these being wellreceived and no objections being returned by 23 June, the earliest thatconstruction could start would be summer of 2007, with completion in summer2008.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for moreinformation if required.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for moreinformation if required.