Written Question · S2W-25330 · Session 2
What steps would normally be taken to ascertain that best value was achieved in relation to the contract to realign the Back O’Hill Road, g…
The question
To ask the Scottish Executive what steps would normally be taken to ascertain that best value was achieved in relation to the contract to realign the Back O’Hill Road, given that Stirling Council appear to have been client, designer and contractor.
The answer
The Back O’Hill Road is a local road and therefore the contract to realign this route is thestatutory responsibility of Stirling Council. The Scottish Executive has put inplace best value arrangements which require continuous improvement in the dischargeof local authority functions. These arrangements are subject to a rolling programmeof monitoring by Audit Scotland.
In the Official Report
No contribution in the Official Report cites S2W-25330 by reference.