Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S2W-24497 · Session 2

Further to the answer to question S2W-23957 by Allan Wilson on 14 March 2006, whether this answer indicates that, if construction of an ele…

Answered Asked by Alex Neil SNP Lodged 21 Mar 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-23957 by Allan Wilson on 14 March 2006, whether this answer indicates that, if construction of an electricity-generating station with capacity of less than 50 megawatts is proposed, consent from Scottish ministers is not required for construction to commence.

The answer

Answered by Allan Wilson on 10 Apr 2006 · 20 days after it was lodged, on time

The Electricity Act sets outthe capacity thresholds above which power stations can only be constructed, operatedor extended with the consent of the Scottish ministers. In most instances the thresholdis 50 megawatts (MW), but in the case of power stations wholly or mainly drivenby water and for all developments beyond the Low Water Mark it is 1 MW.
Any on-shore proposal not inexcess of these thresholds would be subject to the land use planning system, andas such would require approval of the relevant local planning authority. Both ofScotland’s existing nuclear power stations Hunterston “B” and Torness, with installedcapacity of 1190 MW and 1259 MW respectively, exceed these thresholds.

In the Official Report

No contribution in the Official Report cites S2W-24497 by reference.