Further to the answer to question S2W-23957 by Allan Wilson on 14 March 2006, whether this answer indicates that Scottish ministers will wi…

Answered Asked by Alex Neil SNP Lodged 21 Mar 2006

The question

To ask the Scottish Executive, further to the answer to question S2W-23957 by Allan Wilson on 14 March 2006, whether this answer indicates that Scottish ministers will withhold consent under section 36(1) of the Electricity Act 1989 if construction of a new nuclear power station is proposed and the Executive remains unsatisfied that the waste management issue is resolved.

The answer

Answered by Allan Wilson on 16 May 2006 · 56 days after it was lodged, 26 days after it was due

In accordance with ministers’duties under the Electricity Act 1989 any application to construct a new nuclearpower station would be fully considered on its individual merits. However, the Executive’spolicy, as stated in the Partnership Agreement, creates a presumption against the Executive granting consent to such an application while waste management issuesremain unresolved.