Further to the answer to question S2O-8958 by Tavish Scott on 9 February 2006, whether it will provide the details of any agreement reached…

Answered Asked by Fiona Hyslop SNP Lodged 10 Feb 2006

The question

To ask the Scottish Executive, further to the answer to question S2O-8958 by Tavish Scott on 9 February 2006, whether it will provide the details of any agreement reached with Network Rail in respect of the early double tracking of the Edinburgh to Bathgate line and when such agreement was reached

The answer

Answered by Tavish Scott on 23 Mar 2006 · 41 days after it was lodged, 13 days after it was due

Network Rail are continuing todevelop a programme for the early delivery of the double tracking for diesel serviceseast of Bathgate and they have regular discussions with Transport Scotland overthis issue.
As indicated in my statementon 16 March we have reached agreement with Network Rail for the delivery of theearly works. The final details of the agreement are still being developed. Oncethese details are finalised we aim to sign an implementation agreement by the endof 2006.
Transport Scotland hasthe operational responsibility for this area, and can be contacted for more informationif required.

In the Official Report