Written Question · S2W-22411 · Session 2
How much in real terms was spent on building the A9 trunk road from Inverness to Thurso from April 1975 to April 2005, showing also the cos…
The question
To ask the Scottish Executive how much in real terms was spent on building the A9 trunk road from Inverness to Thurso from April 1975 to April 2005, showing also the costs of building the (a) Kessock, (b) Ardullie and (c) Dornoch bridges.
The answer
Records are not available for most construction work undertaken such a long time ago. The details that are available are shown in the following table. These costs have been adjusted to their 2005 equivalent value.
Transport Scotland has the operational responsibility for this area and can be contacted for more information if required.
Construction Project
| Cost Projected To 2005 Values
(£ millions)
Kessock Bridge
| £83.90
Cromarty Bridge
| £19.91
Dornoch Bridge
| £21.79
Longman to Charlestown
| £4.96
Charlestown to Tore
| £19.58
Tore to Duncanston
| £7.72
Duncanston to Ardullie
| £15.81
Dunbeath
| £8.31
Garrick Bridge to Logie Easter
| £6.95
Helmsdale to Ord of Caithness
| £7.00
Transport Scotland has the operational responsibility for this area and can be contacted for more information if required.
Construction Project
| Cost Projected To 2005 Values
(£ millions)
Kessock Bridge
| £83.90
Cromarty Bridge
| £19.91
Dornoch Bridge
| £21.79
Longman to Charlestown
| £4.96
Charlestown to Tore
| £19.58
Tore to Duncanston
| £7.72
Duncanston to Ardullie
| £15.81
Dunbeath
| £8.31
Garrick Bridge to Logie Easter
| £6.95
Helmsdale to Ord of Caithness
| £7.00
In the Official Report