Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S2W-22411 · Session 2

How much in real terms was spent on building the A9 trunk road from Inverness to Thurso from April 1975 to April 2005, showing also the cos…

Answered Asked by Rob Gibson SNP Lodged 18 Jan 2006

The question

To ask the Scottish Executive how much in real terms was spent on building the A9 trunk road from Inverness to Thurso from April 1975 to April 2005, showing also the costs of building the (a) Kessock, (b) Ardullie and (c) Dornoch bridges.

The answer

Answered by Tavish Scott on 30 Jan 2006 · 12 days after it was lodged, on time

Records are not available for most construction work undertaken such a long time ago. The details that are available are shown in the following table. These costs have been adjusted to their 2005 equivalent value.
Transport Scotland has the operational responsibility for this area and can be contacted for more information if required.
Construction Project
| Cost Projected To 2005 Values
(£ millions)

Kessock Bridge
| £83.90

Cromarty Bridge
| £19.91

Dornoch Bridge
| £21.79

Longman to Charlestown
| £4.96

Charlestown to Tore
| £19.58

Tore to Duncanston
| £7.72

Duncanston to Ardullie
| £15.81

Dunbeath
| £8.31

Garrick Bridge to Logie Easter
| £6.95

Helmsdale to Ord of Caithness
| £7.00

In the Official Report

No contribution in the Official Report cites S2W-22411 by reference.