The question
To ask the Scottish Executive whether the £5 million to build a new car park at Croy railway station, announced by the Minister for Enterprise, Transport and Lifelong Learning on 21 March 2002 (Official Report c. 10468) and included in Scotland's Transport: Delivering Improvements, is still available for the project and, if so, when the construction will start.
The answer
Strathclyde Passenger Transport Authority (SPTA) are responsible for the delivery of the new car park at Croy railway station, using the £5 million Scottish Executive award. Part of this award has been spent on acquisition of the land and the provision of a bus interlink service connecting with train arrivals and departures. The remaining budgetary provision is still available in financial year 2006-07 to cover the construction costs. SPTA has commissioned First ScotRail to produce a development proposal and are currently awaiting a detailed timetable for delivery.
I am very concerned about the continued delays in delivering this much-needed facility. The Executive’s grant is available until the end of March 2007, and I therefore expect construction to begin shortly to ensure completion by then.
I am very concerned about the continued delays in delivering this much-needed facility. The Executive’s grant is available until the end of March 2007, and I therefore expect construction to begin shortly to ensure completion by then.
In the Official Report