When it will make an announcement on the proposal to increase the generating capacity of the existing wind-powered generating station at Pa…

Answered Asked by Maureen Macmillan Lab Lodged 21 Dec 2005

The question

To ask the Scottish Executive when it will make an announcement on the proposal to increase the generating capacity of the existing wind-powered generating station at Paul’s Hill in Moray.

The answer

Answered by Allan Wilson on 18 Jan 2006 · 28 days after it was lodged, on time

I can announce that the Scottish ministers have granted consent for this proposal in terms of section 36 of the Electricity Act 1989. This will increase capacity at the wind farm to 65 Megawatts.
This announcement follows a lengthy consultation process which involved environmental groups, government bodies and members of the public. Conditions were attached to this consent to safeguard local and environmental interests.