Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-21851 · Session 2

Further to the answer to question S2W-21290 by Tavish Scott on 15 December 2005, whether, if it accepts the logic of bypassing Muirhead, Ch…

Answered Asked by Alex Neil SNP Lodged 16 Dec 2005

The question

To ask the Scottish Executive, further to the answer to question S2W-21290 by Tavish Scott on 15 December 2005, whether, if it accepts the logic of bypassing Muirhead, Chryston and Moodiesburn with the upgraded A80, it considers it logical to bypass Cumbernauld as part of the upgrade as well and what the reasons are for its position on the issue.

The answer

Answered by Tavish Scott on 18 Jan 2006 · 33 days after it was lodged, on time

Constructing an on line upgrade through Muirhead, Moodiesburn and Chryston would be impractical due to the significant degree of frontage access on that section of the route. The limited frontage access on the remainder of the route can be accommodated through the provision of an alternative access.

In the Official Report

No contribution in the Official Report cites S2W-21851 by reference.