To what extent it would have a role in any decision to extend the life of existing nuclear power stations and whether any further consents …

Answered Asked by Richard Lochhead SNP Lodged 9 Dec 2005

The question

To ask the Scottish Executive to what extent it would have a role in any decision to extend the life of existing nuclear power stations and whether any further consents would be required should any such decision involve refurbishment or new construction.

The answer

Answered by Allan Wilson on 21 Dec 2005 · 12 days after it was lodged, on time

Any decision to allow an extension to the life of an existing power station would be for the Nuclear Installations Inspectorate, the independent body which sets the duration and conditions of the relevant operating licences..
The consent of Scottish ministers, under Section 36(1) of the Electricity Act 1989, would be required for new construction or to increase the output capacity of an existing generating plant to exceed 50 Mega Watts. Investment in the refurbishment of an existing nuclear plant in order to comply with the terms of an operating licence extension would not require Scottish ministers’ approval.

In the Official Report

No contribution in the Official Report cites S2W-21573 by reference.