Written Question · S2W-21465 · Session 2

When each phase of the upgrade and refurbishment of Waverley Station will (a) begin and (b) be completed and how much it envisages each pha…

Answered Asked by David Davidson Con Lodged 6 Dec 2005

The question

To ask the Scottish Executive when each phase of the upgrade and refurbishment of Waverley Station will (a) begin and (b) be completed and how much it envisages each phase will cost.

The answer

Answered by Tavish Scott on 19 Dec 2005 · 13 days after it was lodged, on time

The construction work for Phase 1 of the re-development of Waverley Station will commence in January 2006. The target date for completion of Phase 1 is November 2007. The Scottish Executive is fully funding Phase 1 of the redevelopment of Waverley Station at an estimated cost of £150 million.