Written Question · S2W-21465 · Session 2
When each phase of the upgrade and refurbishment of Waverley Station will (a) begin and (b) be completed and how much it envisages each pha…
The question
To ask the Scottish Executive when each phase of the upgrade and refurbishment of Waverley Station will (a) begin and (b) be completed and how much it envisages each phase will cost.
The answer
The construction work for Phase 1 of the re-development of Waverley Station will commence in January 2006. The target date for completion of Phase 1 is November 2007. The Scottish Executive is fully funding Phase 1 of the redevelopment of Waverley Station at an estimated cost of £150 million.
In the Official Report
No contribution in the Official Report cites S2W-21465 by reference.