Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S2W-21381 · Session 2

Whether it will provide an update on proposals to carry out major resurfacing works on the Broxden roundabout in February/March 2006.

Answered Asked by Andrew Arbuckle LD Lodged 5 Dec 2005

The question

To ask the Scottish Executive whether it will provide an update on proposals to carry out major resurfacing works on the Broxden roundabout in February/March 2006.

The answer

Answered by Tavish Scott on 19 Dec 2005 · 14 days after it was lodged, on time

BEAR Scotland Ltd has completed its study into road safety at Broxden roundabout and has recommended a number of proposals to improve road safety at this location. These improvements will be carried out as part of the second phase of maintenance works on the Perth Southern Bypass, currently programmed for spring 2006.

In the Official Report

No contribution in the Official Report cites S2W-21381 by reference.