Written Question · S2W-21288 · Session 2
What projections it has made in respect of the volume of traffic per day on the A80 in (a) 10, (b) 20 and (c) 30 years time.
The question
To ask the Scottish Executive what projections it has made in respect of the volume of traffic per day on the A80 in (a) 10, (b) 20 and (c) 30 years time.
The answer
Projections have been made for the years 2010 and 2025 for the existing A80 (do minimum) and for the upgrading of the route to motorway status (with scheme). Volumes vary along the route. Typical values are shown in the following tables:
Do Minimum
Route Section
| 2010 Annual Average Daily Flow
| 2025 Annual Average Daily Flow
Muirhead to Mollinsburn
| 49,000 – 53,000
| 48,000 – 54,000
Mollinsburn to Low Wood (Auchenkilns)
| 86,000
| 89,000
Auchenkilns to Castlecary
| 87,000 – 91,000
| 93,000 – 99,000
With Scheme
Route Section
| 2010 Annual Average Daily Flow
| 2025 Annual Average Daily Flow
Muirhead to Mollinsburn
| 5,000 – 8,000
| 7,000 – 9,000
Mollinsburn to Low Wood (Auchenkilns)
| 123,000
| 134,000
Auchenkilns to Castlecary
| 104,000 – 107,000
| 111,000
Do Minimum
Route Section
| 2010 Annual Average Daily Flow
| 2025 Annual Average Daily Flow
Muirhead to Mollinsburn
| 49,000 – 53,000
| 48,000 – 54,000
Mollinsburn to Low Wood (Auchenkilns)
| 86,000
| 89,000
Auchenkilns to Castlecary
| 87,000 – 91,000
| 93,000 – 99,000
With Scheme
Route Section
| 2010 Annual Average Daily Flow
| 2025 Annual Average Daily Flow
Muirhead to Mollinsburn
| 5,000 – 8,000
| 7,000 – 9,000
Mollinsburn to Low Wood (Auchenkilns)
| 123,000
| 134,000
Auchenkilns to Castlecary
| 104,000 – 107,000
| 111,000