What action it is taking to improve the delivery of its central heating replacement programme in order to ensure that those who qualify und…

Answered Asked by Michael Matheson SNP Lodged 23 Nov 2005

The question

To ask the Scottish Executive what action it is taking to improve the delivery of its central heating replacement programme in order to ensure that those who qualify under the programme do not have to wait for periods of up to five months without heating before a new system is installed.

The answer

Answered by Johann Lamont on 6 Dec 2005 · 13 days after it was lodged, on time

I have asked Angiolina Foster, Chief Executive of Communities Scotland, to respond. Her response is as follows:
From the time of application until the installation of the central heating system, the average waiting time is five months. However, many applicants to the programme receive their heating system more quickly. Many householders also require gas connections, electrical upgrades, planning permission or building warrants. Unfortunately, these additional requirements can result in householders waiting five months or more.
The programme is continually monitored and kept under review to ensure that qualifying householders receive their central heating system a quickly as possible after application.