Whether all the necessary planning consents and land purchases are in place for the A68 Dalkeith northern bypass.

Answered Asked by Mark Ballard Green Lodged 21 Nov 2005

The question

To ask the Scottish Executive whether all the necessary planning consents and land purchases are in place for the A68 Dalkeith northern bypass.

The answer

Answered by Tavish Scott on 5 Dec 2005 · 14 days after it was lodged, on time

The necessary planning consent for the scheme was confirmed under the Roads (Scotland) Act 1984 and the Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947 in 1993.
Land for settling ponds is being acquired by agreement.

In the Official Report

No contribution in the Official Report cites S2W-20880 by reference.