The question

To ask the Scottish Executive, further to the answer to question S2W-19065 by Tavish Scott on 20 September 2005, when its officials last met Strathclyde Passenger Transport and whether the proposal to construct a dynamic loop on the Glasgow to Kilmarnock railway line was discussed.

The answer

Answered by Tavish Scott on 5 Oct 2005 · 12 days after it was lodged, on time

The Scottish Executive is in regular contact with Strathclyde Passenger Transport on a number of issues. Officials met late June 2005 to discuss the dynamic loop on the Glasgow to Kilmarnock line. There remains outstanding issues to take forward following that meeting.

In the Official Report

No contribution in the Official Report cites S2W-19480 by reference.