Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S2W-19422 · Session 2

Further to the answer to question S1W-31635 by Lewis Macdonald on 28 November 2002, whether it has reassessed what level of traffic it cons…

Answered Asked by Murdo Fraser Con Lodged 21 Sep 2005

The question

To ask the Scottish Executive, further to the answer to question S1W-31635 by Lewis Macdonald on 28 November 2002, whether it has reassessed what level of traffic it considers is required before a trunk road, such as the A9, should be upgraded to dual carriageway status.

The answer

Answered by Tavish Scott on 5 Oct 2005 · 14 days after it was lodged, on time

The level of traffic required before a trunk road is upgraded to dual carriageway has not been reassessed since Lewis Macdonald’s answer to question S1W-31635 on 28 November 2002. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.scottish.parliament.uk/webapp/wa.search.

In the Official Report