When it will make an announcement on the proposal to build a maximum 3 megawatt hydro-electric generating scheme at River E, near Loch Mhor…

Answered Asked by Maureen Macmillan Lab Lodged 20 May 2005

The question

To ask the Scottish Executive when it will make an announcement on the proposal to build a maximum 3 megawatt hydro-electric generating scheme at River E, near Loch Mhor, Inverness-shire.

The answer

Answered by Allan Wilson on 23 May 2005 · 3 days after it was lodged, on time

I can announce that the Scottish ministers have granted consent to this proposal in terms of section 36 of the Electricity Act 1989. Additionally, this consent carries deemed planning permission in terms of the Town and Country Planning (Scotland) Act 1997.