Whether it will fund any shortfall in the final costs of the Waverley Line, over and above the £151 million already identified.

Answered Asked by David Mundell Con Lodged 17 May 2005

The question

To ask the Scottish Executive whether it will fund any shortfall in the final costs of the Waverley Line, over and above the £151 million already identified.

The answer

Answered by Nicol Stephen on 2 Jun 2005 · 16 days after it was lodged, on time

Responsibility for identifying and securing any additional funding required for the project rests with the bill promoters.

In the Official Report

1 contribution mention S2W-16645
  1. 27 Jun 2007
    Transport
    Christine Grahame SNP Plenary

    That woke me up.I welcome the commitment by the Minister for Transport, Infrastructure and Climate Change to the re-establishment of the Borders railway by means of the Waverley Railway (Scotland) Act 2006. Of course, I am concerned about …