Written Question · S2W-16617 · Session 2
What monitoring procedures are required for the safe implementation of electrical work as a consequence of the Building (Scotland) Act 2003.
The question
To ask the Scottish Executive what monitoring procedures are required for the safe implementation of electrical work as a consequence of the Building (Scotland) Act 2003.
The answer
I have asked Dr Paul Stollard, Chief Executive of the Scottish Building Standards Agency (SBSA), to answer. His response is as follows:
Where work is the subject of a Certificate of Construction, compliance is certified by the installer through a certification system operated by a Scheme Provider appointed by Scottish ministers.
Where work is not the subject of a Certificate of Construction, it is the duty of the local authority, as verifier, to make reasonable enquiry to determine compliance.
Where work is the subject of a Certificate of Construction, compliance is certified by the installer through a certification system operated by a Scheme Provider appointed by Scottish ministers.
Where work is not the subject of a Certificate of Construction, it is the duty of the local authority, as verifier, to make reasonable enquiry to determine compliance.
In the Official Report
No contribution in the Official Report cites S2W-16617 by reference.