Written Question · S2W-16107 · Session 2
What assessment it has made of the progress of the operation of the contract for HM Prison Kilmarnock in comparison with the financial proj…
The question
To ask the Scottish Executive what assessment it has made of the progress of the operation of the contract for HM Prison Kilmarnock in comparison with the financial projection contained in Schedule P to Minute of Agreement between the Secretary of State for Scotland and Kilmarnock Prison Services Limited for the Design, Construction, Management and Financing of a Prison at Kilmarnock.
The answer
I have asked Tony Cameron, Chief Executive of the Scottish Prison Service (SPS) to respond. His response is as follows:
The SPS sees no benefit in doing such an assessment.
The SPS sees no benefit in doing such an assessment.
In the Official Report
No contribution in the Official Report cites S2W-16107 by reference.