The question

To ask the Scottish Executive, further to the answer to question S2W-15179 by Patricia Ferguson on 22 March 2005, whether it will provide a breakdown of the funding provided by the lead applicant and its funding partners for each of the projects.

The answer

Answered by Patricia Ferguson on 21 Apr 2005 · 29 days after it was lodged, on time

This information is set out in the table.
Lead Applicant
Project
| Contribution From

| Total contribution by lead partner and its other funding partners*
| Lead Applicant
| Other funding Partners*
|
Falkirk Council
Westfield Stadium
| £5,000,000**
|
-
| £5,000,000

Stirling Council:
Forthbank
| £17,000,000**
| £1,500,000
| £18,500,000

City of Edinburgh Council:
Sighthill Park
| Amount being reviewed
|
| £44,000,000

Hunters Hall
| Amount being reviewed
|
| £26,000,000

Royal Commonwealth Pool
| Amount being reviewed
|
| £27,000,000

Aberdeen City Council:
Linksfield
| £6,000,000
| £6,000,000***
| £17,000,000

Glasgow City Council:
East End
|
£15,000,000
|
-
| £15,000,000

Scotstoun
| £7,000,000
|
-
| £7,000,000

Toryglen
| £8,000,000
|
-
| £8,000,000

North Lanarkshire Council
Ravenscraig
| £8,200,000
| £5,000,000
| £13,200,000

Notes:
*This excludes the contribution by the Executive and sportscotland which is already covered in the answer to S2W-15548 (answered on 21 April 2005).
**Exact amount to be confirmed.
***Balance to be confirmed.

In the Official Report

No contribution in the Official Report cites S2W-15549 by reference.