What its estimate is of the amount of public funding required to finance PPP projects (a) in each of the last seven years and (b) which are…

Answered Asked by Stewart Stevenson SNP Lodged 17 Feb 2005

The question

To ask the Scottish Executive what its estimate is of the amount of public funding required to finance PPP projects (a) in each of the last seven years and (b) which are repayable in each of the next 15 years.

The answer

Answered by Tom McCabe on 17 Mar 2005 · 28 days after it was lodged, on time

Theestimated annual expenditure to service PPP projects undertaken by public sectorbodies over the period requested is shown in the table below.
Existing Deals (Operational andSigned): Total Estimated Service Payments (in Cash Terms)
Year
| Amount
(£ Million)

1997-98
| 13.8

1998-99
| 28.0

1999-2000
| 83.7

2000-01
| 108.9

2001-02
| 226.7

2002-03
| 297.8

2003-04
| 364.4

2004-05
| 380.7

2005-06
| 413.5

2006-07
| 431.5

2007-08
| 453.0

2008-09
| 455.5

2009-10
| 461.6

2010-11
| 470.6

2011-12
| 479.9

2012-13
| 491.2

2013-14
| 496.2

2014-15
| 507.6

2015-16
| 527.4

2016-17
| 531.5

2017-18
| 545.6

2018-19
| 555.0