Answered Asked by Irene Oldfather Lab Lodged 7 Feb 2005

The question

To ask the Scottish Executive what progress is being made on the Glasgow Crossrail project.

The answer

Answered by Nicol Stephen on 14 Feb 2005 · 7 days after it was lodged, on time

Supported by a Scottish Executive Integrated Transport Fund award of £0.5 million, Strathclyde Passenger Transport has appointed the consultants Scott Wilson to undertake a feasibility study into the proposed Crossrail scheme. The study’s findings are expected in mid-June.

In the Official Report

No contribution in the Official Report cites S2W-14229 by reference.