SPCB Written Question · S2W-11746 · Session 2
What the estimated total running costs will be for Holyrood for each of the next five years.
The question
To ask the Scottish Parliamentary Corporate Body what the estimated total running costs will be for Holyrood for each of the next five years.
The answer
Forecasts have not been submittedbeyond 2006-07 and cost histories will enable future years’ budgets to be setwith greater certainty. The estimated total running costs for Holyrood accommodation(based on existing fabric and building services), for rent, rates, planned andreactive building maintenance, cleaning, and utilities, up to 2006‑07 areas follows:
2004-05
| £5,465,500
2005-06
| £5,994,600
2006-07
| £6,011,700
The estimate for 2004-05 isa combination of interim and Holyrood accommodation costs and allows for doublerunning over the migration period.
The rates for Holyrood havenot yet been set by the assessor, and an estimated cost of £4 million has beenused for budgetary purposes, as advised to the Finance Committee on 5 October 2004.
2004-05
| £5,465,500
2005-06
| £5,994,600
2006-07
| £6,011,700
The estimate for 2004-05 isa combination of interim and Holyrood accommodation costs and allows for doublerunning over the migration period.
The rates for Holyrood havenot yet been set by the assessor, and an estimated cost of £4 million has beenused for budgetary purposes, as advised to the Finance Committee on 5 October 2004.
In the Official Report
No contribution in the Official Report cites S2W-11746 by reference.