Written Question · S2W-11453 · Session 2
With reference to Renewables Obligation – Ofgem’s first annual report: February 2004, why there is a planned reduction in hydro-electric ou…
The question
To ask the Scottish Executive, with reference to Renewables Obligation – Ofgem’s first annual report: February 2004, why there is a planned reduction in hydro-electric output of up to 60mw.
The answer
Only hydro schemes with a declared net capacity of up to 20 MW in size are eligible for support under the Renewables Obligations. A number of hydro schemes were down-rated in order to be eligible for such assistance; the decision to do so was a matter for the generators concerned. Down-rating does not necessarily mean that output will also reduce.
In the Official Report
No contribution in the Official Report cites S2W-11453 by reference.