Written Question · S2W-11385 · Session 2
Further to the answer to question S2W-1153 by Ross Finnie on 4 August 2003, what the results were of Scottish Water’s comprehensive evaluat…
The question
To ask the Scottish Executive, further to the answer to question S2W-1153 by Ross Finnie on 4 August 2003, what the results were of Scottish Water’s comprehensive evaluation of the impact and scale of leakage on the water network, broken down by area.
The answer
I have asked Jon Hargreaves, Chief Executive of Scottish Water, to reply. His response is as follows:
Improving leakage rates on the public water network is a long-term objective of Scottish Water and our evaluation of leakage on the network continues to be ongoing. A large part of Scottish Water’s focus to date has been to establish District Metered Areas (DMAs) and during the current investment period (2002-06) DMAs are being set up on 60% of the water network. These DMAs support the development of area-specific leakage strategies, which can involve identifyingand fixing leaks as well as installing pressure management systems to reduce theamount of water lost.
The establishment of DMAs is being prioritised in areas where leakage is highas well as areas known to have a supply-demand deficit. Areas where we are establishing DMAs include Glasgow, Lanarkshire, Ayrshire, Argyll and Bute, Dumfries and Galloway, Inverness, Fife, Dundee, and Edinburgh. New corporate systems are being developed in parallel that will allow cost and leakage performance data to be captured and analysed. For each area this analysis of level of leakage and operational costs enables the determination of the economic level of leakage which will in future be used to prioritise investment in leakage reduction.
Improving leakage rates on the public water network is a long-term objective of Scottish Water and our evaluation of leakage on the network continues to be ongoing. A large part of Scottish Water’s focus to date has been to establish District Metered Areas (DMAs) and during the current investment period (2002-06) DMAs are being set up on 60% of the water network. These DMAs support the development of area-specific leakage strategies, which can involve identifyingand fixing leaks as well as installing pressure management systems to reduce theamount of water lost.
The establishment of DMAs is being prioritised in areas where leakage is highas well as areas known to have a supply-demand deficit. Areas where we are establishing DMAs include Glasgow, Lanarkshire, Ayrshire, Argyll and Bute, Dumfries and Galloway, Inverness, Fife, Dundee, and Edinburgh. New corporate systems are being developed in parallel that will allow cost and leakage performance data to be captured and analysed. For each area this analysis of level of leakage and operational costs enables the determination of the economic level of leakage which will in future be used to prioritise investment in leakage reduction.
In the Official Report
No contribution in the Official Report cites S2W-11385 by reference.