Written Question · S2W-11169 · Session 2

Further to the answer to question S2W-9859 by Nicol Stephen on 17 September 2004, whether the table showing major trunk road works under wa…

Answered Asked by Fergus Ewing SNP Lodged 4 Oct 2004

The question

To ask the Scottish Executive, further to the answer to question S2W-9859 by Nicol Stephen on 17 September 2004, whether the table showing major trunk road works under way will be developed further to include additional columns showing (a) indicative cost bands, illustrating the relative size of each project, (b) the status of consents and (c) if applicable, any public inquiries to indicate possible factors which might jeopardise the estimated start date.

The answer

Answered by Nicol Stephen on 1 Nov 2004 · 28 days after it was lodged, on time

he information with regard to costs is shown in the following table. These are estimated costs as at 1 September 2004, exclude VAT, and may be subject to change as schemes progress. The table, as published in response to S2W-9859, already shows the position with respect to draft and finalised roads orders, and indicates where public inquiries are known or expected. Again, this information is subject to change over time. Progress on schemes is subject to completion of the necessary statutory procedures, and the availability of finance.
Road
| Scheme
| Summary Description
| Est. Cost (£M) @1/9/04
| Estimated Start Date
| Estimated Completion Date
| Notes

A1
| Thistly Cross to Bowerhouse.
| Construction of new 0.8km dual carriageway
| 2.86
| Under construction
| Q1-2005-06
| Final planned section of dualling of A1

A68
| Soutra South to Oxton.
| Improve Southbound overtaking & Oxton junction
| 4.30
| Q1-2006-07
| Q1-2007-08
| Consultant appointed
- In preparation

A68
| Pathhead to Tynehead Junction.
| Provide 1.9km of improved overtaking opportunities
| 7.76
| Q1-2006-07
| Q1-2007-08
| Consultant appointed
- In preparation

A7
| Auchenrivock.
| Improvement of 2.3km single carriageway to provide overtaking opportunities
| 4.70
| Q4-2005-06
| Q4-2006-07
| Consultant appointed
- In preparation

A7
| Glenmayne to Yair.
| Improvement of 1.7km single carriageway to provide overtaking opportunities
| 4.90
| Q3-2005-06
| Q3-2006-07
| Consultant appointed
- In preparation

A75
| Cairntop to Barlae.


| 2.2km Overtaking scheme
| 4.60
| Q4-2005-06
| Q3-2006-07
| Consultant appointed
- In preparation

A75
| Newton Stewart
| To provide guaranteed westbound overtaking on existing incline.
| 1.84
| Q2-2005-06
| Q4-2005-06
| Consultant appointed
- In preparation

A75
| Barfill to Bettyknowes.
| Provision of overtaking opportunities over 1.2km section.
| 2.59
| Q1-2005-06
| Q1-2006-07
| Consultant appointed
- In preparation

A75
| Planting End to Drumflower
| Provision of 1.5km overtaking opportunities.
| 2.84
| Q2-2005-06
| Q4-2005-06
| Consultant appointed
- In preparation

A75
| Dunragit Re‑alignment.
| Rail bridge replacement and provision of 3km of overtaking opportuniti

In the Official Report

1 contribution mention S2W-11169
  1. 9 Nov 2004
    Budget Process 2005-06
    Fergus Ewing SNP Local Government and Transport Committee

    I want to raise another matter that is mentioned in your submission. Many projects—not least the building in which we are sitting—fall prey to delays. According to the answer to parliamentary question S2W-11169 that I received, work on com…